Photos: IU School of Medicine Research III

Research III Facts:
  • Cost: $83.3M 1
  • Location: Walnut St., between University Blvd. and Barnhill Dr.
  • Height: 7 stories 2
  • Floor Space: 254,000 sq.ft. (118 laboratories) 1
  • Connections: directly connected to Research II and the Cancer Research Institute -- these three buildings together will have 500,000 sq.ft. of research space -- as well as the Clarian People Mover
  • Groundbreaking: October 2005 1
  • Expected Occupancy: early 2009
Rendering, looking NW, People Mover
over Walnut St. in the foregound


Looking NE

Looking NW

People Mover connection to the building

The walkway

Cornerstone 2009

Looking west along Walnut St., Cancer Research Institute in red
brick and the Riley Hospital Tower expansion in the distance.

Again, looking west with Research II in red brick at right
and Research III beyond the People Mover walkway.

1Funding, size, groundbreaking information
2Emporis height information

Thursday, August 14, 2008

Photos: Fairbanks Hall Completion

Fairbanks Hall appears largely complete. Its official opening is scheduled for September but from the look of the parking lot -- yes, unfortunately we have a brand new, enormous, gated surface parking lot to go with this building -- it seems that there are already quite a few people working there. Below is a look at the exterior. You can read more detailed information about the building and compare these photos to earlier construction photos here.

I'm not sure if there will be public access to the interior of this building but I'll see if I can get inside to capture some pictures in the future.

Friday, March 28, 2008

This n' That

Indiana Avenue Restaurant and Lounge: Exterior work continues. They've added three more windows to the Indiana-side roof in addition to the one I showed previously. A number of windows have also been added to the new third-floor space on the North St. side.

IUPUI: Research III is shaping up nicely. This is the last in a trio of interconnected laboratory buildings being built on Walnut St. near University Hospital. With the long-term goal of recruiting 90 faculty members -- as well as the hundreds of associated staff members and students that will work in the labs located in this building -- this represents a significant investment in Indianapolis as a life science hub. Work on the north-side facade is virtually complete and they appear to be in the final stages of work on the south-side facade and People Mover connection. The building is expected to be occupied in December. As the weather continues to warm up, expect to see pictures of this project sometime soon. Research III is the taller middle section with the walkway connection in this rendering:


BadaBoomz: Vintage tastings are back! Stop by Saturday (March 29th) and get a taste of Sierra Nevada Bigfoot '00 & '03 as well as Bell's Batch 7000 (imperial stout). $9 gets you a 5oz sample of all three and when they're gone, they're gone.

HD-DVD Update: supplies of players are drying up, indicating that we're just about at the end of the road. The high-end HD-A35 has been gone for weeks and the HD-A30 is now starting to disappear from online shops. Only a handful of shops still carry the entry-level HD-A3 and they won't last much longer. Movies still appear to be widely available, however. My credit card has been getting quite the workout snatching up discs before they're all gone. With a sunk investment in a player, an average of just $9-10 per movie, and a limited-time opportunity, how could I not?! These movies will be MUCH more expensive once they switch over to Blu-ray. Update (12:50pm) Looks like Best Buy just decided to pull all remaining HD-DVD merchandise.

Monday, February 25, 2008

Photos: Fairbanks Hall

IU/Clarian Fairbanks Hall -- The Clarian Education and Resource Center:
  • Cost: $44M (Clarian and IU to split the cost, with a $6M contribution from the Richard M. Fairbanks Foundation for naming rights)
  • Location: East side of Downtown Canal, between 10th St. and 11th St.
  • Height: 6 stories
  • Floor Space: 182,000 sq.ft. (featuring various simulators for training IU Medical/Nursing Students and Clarian Staff)
  • Project Start Date: July, 2006
  • Expected Completion: Summer 2008
A rendering of the finished product


Photos taken September 2007


Photos taken February 2008

Friday, February 1, 2008

Photos: IUPUI Campus Center Interior

I intended to get over to the IUPUI Campus Center a second time this week to add photos to this collection. Unfortunately, it doesn't look like I'll be able to do that. Rather than delay any more, here's the shortened set I took last Friday, January 25th. An additional set may follow at a later date, perhaps when the building is 100% complete. See earlier photos of the exterior here and here.
The Art Deco signage above each of the
three entrances. This is the SE entrance.
The view from below (basement level). Note the
long escalator at left, with landings at each floor.
The gerbil tube connecting the second levels
of the Campus Center and Cavanaugh Hall.
Each department within the Campus Center
features a sign such as this over the door.
There is a small gallery space in the Campus Center
currently showing "Marching Toward Justice: The History
of the 14th Amendment to the United States Constitution."
The view from above (4th floor).
For those that are curious, Starbucks gets the prime spot in the Campus Center: First Floor on the corner of Michigan and University, inside the Barnes & Noble bookstore. It is expected to open in April, though no work had begun as of last week.

Monday, January 28, 2008

Photos: IUPUI Campus Center Bell Tower

Interior photos will follow later this week. See earlier exterior photos here.

Monday, December 31, 2007

Photos: Crossing IUPUI

Editorial Note: I've added a new post topic area called "Photos" that will exclusively contain facts and photos posts with very limited commentary. Renderings and commentary will fall under the "Development" topic area.

IUPUI has a couple new crosswalk markings on New York St. that clearly identify that you're on IUPUI campus. The photos below are the crosswalk at West St., between Inlow Hall and Military Park, though there's at least one more at the intersection with University Blvd.

One of the standard IUPUI logos is at either end of the crosswalk.

A large IUPUI Jaguar logo is at the center.

Thursday, October 18, 2007

Photos: IUPUI Campus Center Update

IUPUI Campus Center Facts:

  • Location: SW corner of University Blvd. and Michigan St.
  • Broke ground: September 30, 2005
  • Cost: $50M (20% from state, 39% from student fees, 41% from revenue generated)
  • Architects: Smithgroup of Washington, DC and Ratio Architects of Indianapolis
  • Height: 179ft to top of bell tower
  • Estimated Completion: December, 2007

Building Overview:













South/Vermont St. facade:













Southeast Corner with Bell Tower:






















Southeast corner and East/University Blvd. facade:













Southeast corner with gerbil tube to Cavanaugh Hall:






















Looking North along the East facade (the fact that this glass wall drops down to the basement level is probably the most interesting feature of the design. With the up-lighting, this facade should look amazing at night):






















Northeast corner (University Hospital Cancer Center addition in the background):













Northeast corner:













Looking West at the North/Michigan St. facade:













Looking East at the North/Michigan St. facade (this facade is terrible -- there isn't even a public door into the building):

















For additional info, renderings and to take a look at the construction webcam, check out IUPUI's Campus Center webpage.